Below are pictures from a couple of our recent projects, chosen specifically to help future homeowners understand Team's general timetable when buiding a new home. Browse through the images to see...
 
  • what may be happening during the next phase of your project (if Team is currently building your house)
  • the rationale for certain aspects of the building process ("why aren't they out there working today???")
  • tips for the future homeowner - when to take pictures, etc.
  • * This is one component of the Team building experience - click here to see the other components *
    PHASE 1
    notes
    PHASE 2
    notes
    PHASE 3
    notes
    Strip & stake the lot
    Dig the basement
    Pour the footings
     
    Wall forms up
    Pour foundation walls
    Wall forms come off
    Let the walls strengthen
    Underslab plumbing
    Basement floor
    Walls gaining strength
    Foundation cross-section
    Pour the garage floor & porch
     
    Walls still strengthening
     
    Septic
    Septic
    Backfill
     
    Framing
     
     
     
    If 2nd Floor
    Roof
     
     
     
    Framing is completed
    Shower & tub
    Windows & doors
    The well
     
     
    Rough heating & plumbing
     
     
    TAKE PICTURES
    TAKE PICTURES
    Insulation
     
     
     
     
    Drywall
     
     
    Driveway & sidewalk
    Lay the brick
    Finishing the drywall
     
     
    Brick patio
     
     
     
    Siding
     
    Siding continues
    Interior paint
     
     
     
     
    Wood floor installed
     
    Trim work begins
     
    Trim work continues
    Cabinets installed
    Trim finished 
     
    Electricians & plumbers back
    Gutters installed
    Kitchen countertops
     
    Final grade
     
    Carpet installed
    Sam
    Final exterior work
    Interior is cleaned
     
    Everything is done!